ECB decides to start construction works for its new premises in spring 2010

Published: 18 December 2009 y., Friday

Europos centrinio banko vadovas Žanas Klodas Trišė (Jean Claude Trichet) dalyvauja spaudos konferencijoje Vokietijoje
The Governing Council of the European Central Bank (ECB) has decided to start the main construction works for its new premises in spring 2010.

This decision was taken on the basis of the positive outcome of the Europe-wide public tendering procedure for the construction works that was conducted in the course of 2009. Following the Governing Council’s decision, Jean-Claude Trichet, President of the ECB, said “ we are delighted that our chosen tendering strategy has been successful and that our expectations have been met.” The President added that “ our future premises, the new home of the ECB and of the euro, will symbolise our values being at the service of fellow European citizens. The new premises will contribute to the development of Frankfurt’s Ostend while respecting the existing Grossmarkthalle. We are looking forward to moving in 2014.” President Trichet has personally informed Lord Mayor Petra Roth about the decision of the Governing Council.

The construction works for the new premises were divided into 12 separate packages, which were further subdivided into a total of 69 lots. The first eight tender packages, namely structural works, on-site infrastructure works, elevators, facades, roofing, height-access systems, mechanical services and electrical services, were sent out to tender during the course of 2009. These eight packages consist of 44 lots and constitute around 80% of the building costs. The tenders submitted by construction companies for the first eight packages are within the budget.

The tendering procedure generated a considerable amount of market interest, with over 400 applications being submitted by large, as well as medium-sized, construction companies from all over Europe. The overall quality of the applications and tenders received was very high. Each application and tender was evaluated according to clear predefined criteria that were published at the beginning of the tendering procedure. The evaluation was conducted by expert teams consisting of ECB representatives, the architect, the planners, the external project manager and the construction manager.

The tendering procedure for the first eight packages is now being finalised and contracts with the construction companies will be signed early next year, with a view to starting the main construction works in spring 2010. It is envisaged that the four remaining tender packages will be put out to tender in the course of 2010.

Further details regarding the new ECB premises can be found on the ECB’s website at http://www.ecb.europa.eu/ecb/premises/ .

 

Šaltinis: www.ecb.int
Copying, publishing, announcing any information from the News.lt portal without written permission of News.lt editorial office is prohibited.

Facebook Comments

New comment


Captcha

Associated articles

The most popular articles

Commission temporarily authorises aid measures for Austrian bank BAWAG P.S.K.

The European Commission has authorised under EU state aid rules a €550 million capital injection and a €400 million guarantee in favour of the Austrian bank BAWAG. P.S.K. The Commission found the measures to be in line with EU state aid rules. more »

Sharpest Decrease in Hourly Labour Costs Recorded in Lithuania

EUROSTAT has reported that the sharpest annual decrease in hourly labour costs of -10.9% was observed in Lithuania in the 3rd quarter of 2009. more »

Changes in the unemployment rate in III quarter 2009

Statistics Lithuania informs that, according to the Labour Force Survey data, the number of the unemployed in III quarter 2009 made 228.1 thousand. more »

The economic recovery in the euro area is gathering momentum, albeit at a modest pace

What has come to be termed as the "Great Recession" seems to have come to an end in the third quarter of 2009. more »

Commission approves Lithuanian short-term export credit insurance scheme

The European Commission has authorised, under EU State aid rules, a measure adopted by Lithuania to limit the adverse impact of the current financial crisis on exporting firms. more »

Tree more directions from Vilnius to European cities

The schedule of Vilnius International Airport (VIA) is supplemented with 3 more new directions; the airline company airBaltic starts regular flights to Paris today, to Munich tomorrow, and to Berlin on Monday. more »

ECB decides to start construction works for its new premises in spring 2010

The Governing Council of the European Central Bank (ECB) has decided to start the main construction works for its new premises in spring 2010. more »

The award to Bank SNORAS from NASDAQ OMX Baltic Stock Exchange

AB Bank SNORAS was granted the award from NASDAQ OMX Baltic Stock Exchange for the jubilee 15-year listing of the bank’s shares on NASDAQ OMX Vilnius Stock Exchange. more »

Parex banka establishes subsidiary for real estate management

Parex banka has established a subsidiary, SIA NIF, which will professionally manage assets that are not related to the Bank’s core business. more »

Commission proposes measures to ensure that Greek farmers can receive EU support payments

Mariann Fischer Boel, European Commissioner for Agriculture and Rural Development, today put forward a plan to ensure that Greece will put in place the systems necessary to allow EU aid payments to be made to farmers. more »