ECB decides to start construction works for its new premises in spring 2010

Published: 18 December 2009 y., Friday

Europos centrinio banko vadovas Žanas Klodas Trišė (Jean Claude Trichet) dalyvauja spaudos konferencijoje Vokietijoje
The Governing Council of the European Central Bank (ECB) has decided to start the main construction works for its new premises in spring 2010.

This decision was taken on the basis of the positive outcome of the Europe-wide public tendering procedure for the construction works that was conducted in the course of 2009. Following the Governing Council’s decision, Jean-Claude Trichet, President of the ECB, said “ we are delighted that our chosen tendering strategy has been successful and that our expectations have been met.” The President added that “ our future premises, the new home of the ECB and of the euro, will symbolise our values being at the service of fellow European citizens. The new premises will contribute to the development of Frankfurt’s Ostend while respecting the existing Grossmarkthalle. We are looking forward to moving in 2014.” President Trichet has personally informed Lord Mayor Petra Roth about the decision of the Governing Council.

The construction works for the new premises were divided into 12 separate packages, which were further subdivided into a total of 69 lots. The first eight tender packages, namely structural works, on-site infrastructure works, elevators, facades, roofing, height-access systems, mechanical services and electrical services, were sent out to tender during the course of 2009. These eight packages consist of 44 lots and constitute around 80% of the building costs. The tenders submitted by construction companies for the first eight packages are within the budget.

The tendering procedure generated a considerable amount of market interest, with over 400 applications being submitted by large, as well as medium-sized, construction companies from all over Europe. The overall quality of the applications and tenders received was very high. Each application and tender was evaluated according to clear predefined criteria that were published at the beginning of the tendering procedure. The evaluation was conducted by expert teams consisting of ECB representatives, the architect, the planners, the external project manager and the construction manager.

The tendering procedure for the first eight packages is now being finalised and contracts with the construction companies will be signed early next year, with a view to starting the main construction works in spring 2010. It is envisaged that the four remaining tender packages will be put out to tender in the course of 2010.

Further details regarding the new ECB premises can be found on the ECB’s website at http://www.ecb.europa.eu/ecb/premises/ .

 

Šaltinis: www.ecb.int
Copying, publishing, announcing any information from the News.lt portal without written permission of News.lt editorial office is prohibited.

Facebook Comments

New comment


Captcha

Associated articles

The most popular articles

Gas Coordination Group sees overall good level of preparedness of EU Member States and Energy Community countries in case of gas crisis

The Gas Coordination Group, chaired by the Commission, met this afternoon to analyze in detail all elements of the preparedness of the EU and the Energy Community for a potential supply disruption in the Winter 2009/2010. more »

Joint statement by Commission and IMF after European Banking Coordination Initiative Meeting for Romania

In a meeting of the European Bank Coordination Initiative Group, held in Brussels, the parent banks of the nine largest banks operating in Romania reaffirmed their commitment to maintain their exposure to the country and ensure adequate capital levels over 10 percent for their affiliates. more »

Lithuania and Vilnius Turning to a More Inviting Destination

Airline airBaltic has informed of its plans to resume some flights from Vilnius International Airport before the end of this year. more »

Commission approves restructuring plan of Lloyds Banking Group

The European Commission has approved under EC Treaty state aid rules the restructuring plan of Lloyds Banking Group. more »

"Finance and climate change" - a challenge for the future

"Finance and climate change" was under discussion at a 10 November hearing in parliament's Industry, Research and Energy Committee. more »

IMF Announces Sale of 2 Metric Tons of Gold to the Bank of Mauritius

The International Monetary Fund announced today the sale of 2 metric tons of gold to the Bank of Mauritius, the nation’s central bank. more »

The new ten winners of Danske Bankas scholarships for the 2009–2010 academic year determined

After lots were drawn, ten winners of Danske Bankas scholarships and one winner of an iPod shuffle player were established. more »

Bank SNORAS begins distributing “Finasta Asset Management” II level pension funds

From 16 November 2009, AB Bank SNORAS network starts providing new products – one can sign agreements of “Finasta Asset Management” II level pension accumulation funds in all subdivisions of the bank. more »

Baltic Rim Outlook: uneven recovery

The expected turnaround in the Baltic Rim economies is likely to gradually improve the business opportunities for Nordic companies operating in the region. more »