ECB decides to start construction works for its new premises in spring 2010

Published: 18 December 2009 y., Friday

Europos centrinio banko vadovas Žanas Klodas Trišė (Jean Claude Trichet) dalyvauja spaudos konferencijoje Vokietijoje
The Governing Council of the European Central Bank (ECB) has decided to start the main construction works for its new premises in spring 2010.

This decision was taken on the basis of the positive outcome of the Europe-wide public tendering procedure for the construction works that was conducted in the course of 2009. Following the Governing Council’s decision, Jean-Claude Trichet, President of the ECB, said “ we are delighted that our chosen tendering strategy has been successful and that our expectations have been met.” The President added that “ our future premises, the new home of the ECB and of the euro, will symbolise our values being at the service of fellow European citizens. The new premises will contribute to the development of Frankfurt’s Ostend while respecting the existing Grossmarkthalle. We are looking forward to moving in 2014.” President Trichet has personally informed Lord Mayor Petra Roth about the decision of the Governing Council.

The construction works for the new premises were divided into 12 separate packages, which were further subdivided into a total of 69 lots. The first eight tender packages, namely structural works, on-site infrastructure works, elevators, facades, roofing, height-access systems, mechanical services and electrical services, were sent out to tender during the course of 2009. These eight packages consist of 44 lots and constitute around 80% of the building costs. The tenders submitted by construction companies for the first eight packages are within the budget.

The tendering procedure generated a considerable amount of market interest, with over 400 applications being submitted by large, as well as medium-sized, construction companies from all over Europe. The overall quality of the applications and tenders received was very high. Each application and tender was evaluated according to clear predefined criteria that were published at the beginning of the tendering procedure. The evaluation was conducted by expert teams consisting of ECB representatives, the architect, the planners, the external project manager and the construction manager.

The tendering procedure for the first eight packages is now being finalised and contracts with the construction companies will be signed early next year, with a view to starting the main construction works in spring 2010. It is envisaged that the four remaining tender packages will be put out to tender in the course of 2010.

Further details regarding the new ECB premises can be found on the ECB’s website at http://www.ecb.europa.eu/ecb/premises/ .

 

Šaltinis: www.ecb.int
Copying, publishing, announcing any information from the News.lt portal without written permission of News.lt editorial office is prohibited.

Facebook Comments

New comment


Captcha

Associated articles

The most popular articles

Georgia: Kakheti Regional Road Improvement Project

The Kakheti Regional Roads Improvement Project for Georgia aims to reduce transport costs and improve access and traffic safety for the Kakheti regional roads. more »

The Cultural Days of the European Central Bank 2009 come to an end

“Don Quixote – Made in Romania” brought the curtain down on the Cultural Days of the European Central Bank (ECB) 2009, with an expressive combination of tap dance, folklore, pantomime and martial arts. more »

The capital of the Latvian bank AS “Latvijas Krajbanka”, managed by Bank SNORAS, increased by LTL 45 million

The Latvian Finance and Capital Market Commission permitted Mr. Vladimir Antonov, who is also the main shareholder of AB Bank SNORAS, to acquire and manage up to 33 per cent of the shareholding of the Latvian bank AS “Latvijas Krajbanka”. more »

New Asphalt Plant

On October 30, the French-capital company “Eurovia Lietuva” opened a new asphalt plant near the capital city Vilnius. The company invested EUR 3.5 million into the new factory which is located near the old manufacturing facility to be closed soon. more »

The shareholders of AB Bank SNORAS endorsed increasing the authorized capital up to LTL 500 million

During the extraordinary general shareholders' meeting of AB Bank SNORAS, which took place on 5th November 2009, it was decided by additional contributions to increase the authorized capital of the bank by more than LTL 88 million. more »

New Asphalt Plant

The French-capital company “Eurovia Lietuva” opened a new asphalt plant near the capital city Vilnius. more »

Baltic Banking Among the Most Advanced in CEE

“Banking Market in the Baltics 2009-2011, CEE Banking Brief” report recently presented by Intelace Research states that, despite the current economic recession, Estonia, Latvia and Lithuania are still among the most advanced banking markets in Central and Eastern Europe (CEE). more »

AB Bank SNORAS will include LTL 72.5 million bond emission in the second level capital of the bank

The Bank of Lithuania permitted AB Bank SNORAS to include in the second level capital LTL 72.5 million (EUR 21 million) worth emission of termless debt securities distributed via non-public distribution on 31st August this year. more »

Financial, Economic and Social Crisis Committee holds opening session

The remit of the Parliamentary Committee set up to examine the financial crisis was debated at its first meeting on Wednesday (4 November). more »

Borderless banking

Europeans can now use direct debit from their home account to pay bills anywhere in the EU. more »