ECB decides to start construction works for its new premises in spring 2010

Published: 18 December 2009 y., Friday

Europos centrinio banko vadovas Žanas Klodas Trišė (Jean Claude Trichet) dalyvauja spaudos konferencijoje Vokietijoje
The Governing Council of the European Central Bank (ECB) has decided to start the main construction works for its new premises in spring 2010.

This decision was taken on the basis of the positive outcome of the Europe-wide public tendering procedure for the construction works that was conducted in the course of 2009. Following the Governing Council’s decision, Jean-Claude Trichet, President of the ECB, said “ we are delighted that our chosen tendering strategy has been successful and that our expectations have been met.” The President added that “ our future premises, the new home of the ECB and of the euro, will symbolise our values being at the service of fellow European citizens. The new premises will contribute to the development of Frankfurt’s Ostend while respecting the existing Grossmarkthalle. We are looking forward to moving in 2014.” President Trichet has personally informed Lord Mayor Petra Roth about the decision of the Governing Council.

The construction works for the new premises were divided into 12 separate packages, which were further subdivided into a total of 69 lots. The first eight tender packages, namely structural works, on-site infrastructure works, elevators, facades, roofing, height-access systems, mechanical services and electrical services, were sent out to tender during the course of 2009. These eight packages consist of 44 lots and constitute around 80% of the building costs. The tenders submitted by construction companies for the first eight packages are within the budget.

The tendering procedure generated a considerable amount of market interest, with over 400 applications being submitted by large, as well as medium-sized, construction companies from all over Europe. The overall quality of the applications and tenders received was very high. Each application and tender was evaluated according to clear predefined criteria that were published at the beginning of the tendering procedure. The evaluation was conducted by expert teams consisting of ECB representatives, the architect, the planners, the external project manager and the construction manager.

The tendering procedure for the first eight packages is now being finalised and contracts with the construction companies will be signed early next year, with a view to starting the main construction works in spring 2010. It is envisaged that the four remaining tender packages will be put out to tender in the course of 2010.

Further details regarding the new ECB premises can be found on the ECB’s website at http://www.ecb.europa.eu/ecb/premises/ .

 

Šaltinis: www.ecb.int
Copying, publishing, announcing any information from the News.lt portal without written permission of News.lt editorial office is prohibited.

Facebook Comments

New comment


Captcha

Associated articles

The most popular articles

European Globalisation Fund set to help workers in clothing industries in Spain

The European Commission approved an application from Spain for assistance from the EU Globalisation Adjustment Fund (EGF). more »

European Commission calls for saving time and money in cross-border legal disputes through mediation

The European Commission today reiterated the potential of existing EU-rules on mediation in cross-border legal disputes, reminding Member States that these measures can only be effective if put in place by Member States at national level. more »

New opportunities for export of animal products to Russia as certificates enter into force

Exports of animals and animal products from the European Union to Russia are expected to receive a boost after five new certificates for exports between the EU and the Russian Federation entered into force on August 15. more »

World Bank President Zoellick Completes Two-Day Visit To Moldova

World Bank Group President Robert B. Zoellick visited Moldova on August 11-12 at the invitation of Prime Minister Vlad Filat. more »

Profit of the first half of 2010 before loan impairment charges of Danske Bank A/S Lithuania branch is 28m LTL

These are the financial results of the banking activities of the Danske Bank Group in Lithuania (Danske Bankas and Danske Lizingas UAB). more »

First European Investment Bank loan to Armenia for Yerevan metro upgrade

The European Investment Bank (EIB) today signed its first loan agreement with Armenia. more »

Commission releases €14.9 million for food security to the Republic of Niger

Given the worsening food crisis in the Sahel, the Commission today agreed to disburse €14.9 million for food security in Niger, the worst affected country in the area. more »

Commission approves the acquisition of joint control of Arnotts by Anglo Irish Bank and RBS

The European Commission has cleared under the EU Merger Regulation the proposed restructuring of Arnotts' debts in return for a transfer of control to Anglo Irish Bank and Royal Bank of Scotland (RBS). more »

European Commission approves €135 million in grants to Morocco for 2010

The European Commission today approved a new financial support package of €135 million for Morocco. more »

The Commission allocates an additional €10 million package in humanitarian aid for Liberia

The European Commission is allocating an extra €10 million in humanitarian aid for Liberia. more »