Commission awards major contracts to make Galileo operational early 2014

Published: 7 January 2010 y., Thursday

Medalis
The European Commission announced today the award of three of the six contracts for the procurement of Galileo’s initial operational capability. The contract for the system support services is awarded to ThalesAleniaSpace of Italy , that for a first order of 14 satellites to OHB System AG of Germany and that for the launch services to Arianespace of France. This will allow the initial deployment and service provision of Europe’s satellite navigation system as of early 2014.

Antonio Tajani, European Commission Vice-President in charge of Transport, said: “With this and the upcoming awards for the remaining procurement packages, we are concluding a critical phase of the Galileo programme. We can now focus on the actual roll-out and demonstrate to European citizens that Europe’s own satellite navigation system is firmly underway”.

The contract awarded to ThalesAleniaSpace for the system support services covers the industrial services needed to support the European Space Agency for the integration and the validation of the Galileo system. It has a value of €85 million.

The signing of a framework contract in December with both OHB System AG and EADS-Astrium GmBH, both of Germany, paved the way for the eventual provision of a maximum of 32 satellites. Today OHB wins the first order of 14 satellites for a value of €566 million. The remaining satellites will be procured in subsequent work orders, each time from either OHB or EADS-Astrium GmBH depending on which company provides the most advantageous offer. The Commission intends to follow a strategy of double sourcing to lower risks, particularly in terms of delivery timings, and increase flexibility.

The contract with Arianespace covers the launch of five Soyuz launchers, each carrying two satellites. The first launch is scheduled for October 2012. The value of the contract amounts to €397 million.

The contracts are expected to be signed in the next few weeks between the chosen companies and the European Space Agency, on behalf of the European Commission.

The Commission is now able to better schedule the timings for the provision of the different Galileo services: the Open Service, the Public Regulated Service and the Search And Rescue Service will be provided as of early 2014. The Safety-of-Life Service and the Commercial Service will be tested as of 2014 and will be provided as Galileo reaches full operational capability with a constellation of 30 satellites.

The remaining three procurement contracts, for the ground mission infrastructure, the ground control infrastructure and the operations should be awarded by mid-2010.

Background

Procurement process

The procurement for Galileo’s full operational capability is divided into six work packages:

system support services

satellites

launch services to put the satellites in orbit

ground mission infrastructure to ensure the provision of the services

ground control infrastructure to manage the satellites

operations.

The process kicked off in July 2008 by the European Space Agency, under delegation from the European Commission. Short-listed companies were invited to submit best and final offers following a comprehensive dialogue phase. All contracts are awarded on the basis of “best value for money”.

For some work packages, both framework contracts and specific contracts may be signed. Framework contracts set the conditions under which specific contracts will be concluded for concrete work orders, but without any commitment regarding the award of such specific contracts.

System support services

Through a framework contract lasting from 2010 till 2016, a specific contract for a first work order was awarded to ThalesAleniaSpace. The specific contract for the first order lasts from 2010 till 2014, and includes the following services:

system engineering

system performance engineering

signal-in-space engineering

security engineering

ground segment engineering

system assembly, integration and verification

product assurance.

Satellites

A framework contract signed with both OHB System AG and EADS-Astrium GmBH lasting from 2010 till 2015, covers the provision of a maximum of 32 satellites. A specific contract for a first order of 14 satellites was awarded to OHB, with the provision of the first satellite in July 2012. One satellite is expected every 1.5 month as of then, with the last one scheduled to be delivered in March 2014.

Launch services

A contract was awarded to Arianespace for the launch of five Soyuz launchers from Kourou, French Guiana, each taking two satellites on board. The first launch is scheduled to take place in October 2012 and will be followed by four to five launches per year. The contract also contains options for either two additional Soyuz launches (carrying two satellites) or one Ariane 5 (carrying four satellites).

Phasing of the programme

The Galileo programme has been structured in two phases:

The in-orbit validation (IOV) phase consists of tests and the operation of four satellites and their related ground infrastructure. This phase is ongoing. The launch of the first two IOV satellites is scheduled for end November 2010, followed by the other two in April 2011.

The full operational capability (FOC) phase consists of the deployment of the remaining ground and space infrastructure. It includes an initial operational capability phase of 18 operational satellites. The full system will consist of 30 satellites, control centres located in Europe and a network of sensor stations and uplink stations installed around the globe.

 

Šaltinis: europa.eu
Copying, publishing, announcing any information from the News.lt portal without written permission of News.lt editorial office is prohibited.

Facebook Comments

New comment


Captcha

Associated articles

Choice boxes - join the conversation across Europe

The need for energy that does not come from oil, equality between the sexes and more spending on education are just some of the things people have requested using the Parliament's choice boxes. more »

Inflation, Monetary Policy and the Economy: the Challenge for Schools and Colleges

This week marks the launch of the tenth Interest Rate Challenge, the competition designed to give 16 to 18 year old students across the UK the opportunity to take on the role of the Bank’s Monetary Policy Committee and set monetary policy for the UK to meet the inflation target of 2.0%. more »

Battery swap boosts electric cars

One California company unveiled a solution - a prototype energy station that swaps electric vehicles' empty batteries for fully charged ones. more »

Minor damage to the space shuttle

NASA officials have confirmed that the space shuttle Atlantis was hit by a piece of debris that nicked part of its heat shield. more »

Space shuttle Atlantis lifts off

Atlantis carried a seven-member crew that was scheduled to perform five spacewalks to install and repair instruments and replace positioning gyroscopes on the telescope, which orbits 350 miles above Earth. more »

The smart soccer pitch

Artificial grass maker Ten Cate is developing an intelligent pitch in the Netherlands. more »

Downturn could 'harm' environment

Russian scientist Olga Speranskaya has taken on one very tough job - to help clean up the vast network of toxic chemical sites in the former Soviet states. more »

Ideas move Europe on spring day

European politicians will be visiting schools around Europe as part of ‘spring day’ 2009. more »

Scientists develop dream recorder

The current experiments show a subject an image and then reconstruct that image based on scans of the brain's visual cortex. more »

Children of immigrants: Yes to new language, No to segregation

The children of people who come to live in Europe will have to learn the language of the country they enter from pre-school age. more »